MLA website redevelopment: user requirements
Project start date: | 26 May 2014 |
Project end date: | 19 June 2015 |
Publication date: | 19 June 2015 |
Project status: | Completed |
Livestock species: | Sheep, Goat, Lamb, Grassfed cattle, Grainfed cattle |
Summary
MLA engaged Lavender in May 2014 to deliver a set of user requirements that are high quality, evidence based and actionable to guide the design and build of the new MLA website.
On 24 December 2014, Lavender was informed by MLA that it was in breach of its obligaitons and to cease work on the project.
It was further stipulated that MLA required a refund of the advance funds paid to Lavender ($96,592.10 incl. GST) less any verified costs incurred by the vendor in connection with the project as at that date.
On 3 February 2015 Lacender provided MLA with a spreadsheet of such project costs incurred totalling $20,979.05 incl. GST. Having verified these costs, MLA then issued an invoice to Lavender on 12 February 2015 in the amount of $75,613.05 in GST, which was paid.